Place
Wittenwil
Date
2024-2027
Services
Development of Retrofit Planning, Preparation of Approval Documents, Support in Primary Technology, Overhead Line, Creation of Tender Documents
The Wittenwil Substation was commissioned in the early 1990s and has since played an important role in the regional power supply. While the outdoor switchyard responsible for power transmission and distribution remains in good condition, the secondary systems and auxiliary installations have reached the end of their technical service life and require replacement to ensure long-term operational reliability.
In addition, the existing facilities are closely interconnected with infrastructure operated by the former asset owner. One of the key objectives of the project is therefore to significantly reduce these dependencies and increase the operational independence of the substation.
The project includes the renewal of the secondary systems and auxiliary installations as well as the construction of a new substation building. This modernization will ensure that the facility meets future requirements of the transmission network while improving operational reliability and maintainability.
The Wittenwil Substation consists of a four-bay air-insulated switchyard (AIS) comprising two transmission line bays and two transformer bays. The single-busbar arrangement is operated without electromechanical busbar sectionalization. The primary equipment remains in good condition and will largely remain unchanged.
The existing secondary systems have reached the end of their technical service life and will be completely renewed as part of the project.
On behalf of Axpo Grid AG, Future Grid Solutions provides support in the following areas:
For more information or inquiries, the team at Future Grid Solutions is happy to assist you. Please feel free to contact us for further details about this project or our other services.