Place

Giswil, Obwalden

Date

2026-2027

Services

Detailed Engineering Design, Preparation of Permitting and Approval Documentation, Preparation of Tender Documents, Construction Supervision and Support, Project Close-Out

As part of the refurbishment of the Giswil Substation, Future Grid Solutions GmbH (FGS) has been commissioned by Swissgrid AG to provide overall project management and engineering services for a temporary 220 kV transmission line arrangement. The objective of the project is to maintain safe and reliable grid operation during the replacement of the substation's secondary systems.

To achieve this, a temporary connection of the extra-high-voltage transmission line will be installed between the existing structures 1490x062 and 1490x064. This measure ensures grid stability throughout the refurbishment works and enables the secure continuation of transmission system operations.

FGS supports the project throughout all project phases. The scope of services includes the engineering and design of the temporary line arrangement, preparation of the documentation required for the simplified planning approval procedure, development of tender documentation, on-site construction support, and project close-out. In addition, FGS provides all required technical verifications and ensures coordination between the client, authorities, landowners, and specialist consultants.

FGS Services

  • Overall Project Management
  • Engineering and Design of the Temporary Transmission Line Arrangement
  • Preparation of the Planning Approval (PGV) Dossier
  • Route Alignment and Overhead Line Design
  • Electrical and Structural Calculations and Verification
  • Coordination of Environmental and Specialist Planning Activities
  • Liaison with Authorities, Landowners, and Technical Stakeholders
  • Preparation of Tender Documents
  • Technical Construction Support and Site Supervision
  • Project Close-Out and Final Documentation

Project Information

Client: Swissgrid AG
Project: Temporary Transmission Line at Giswil Substation (TR1490)
Location: Giswil (OW), Switzerland
Voltage Level: 220 kV
Scope of Services: Overall Project Management, Engineering, Planning Approval Documentation, Tendering, Construction Support, and Project Close-Out